May 30, 2025 | Construction continues on the northbound lane of Bunker Hill Rd. Traffic is restricted to one-way southbound travel only between Memorial and Taylorcrest as work on the northbound lane is completed. Drivers are urged to plan their route accordingly and follow recommended detour signage during construction.

Attempting to travel northbound in the southbound lane at any time is strictly prohibited. MVPD will continue traffic enforcement efforts to ensure the safety of all motorists and construction crews.

Please note that the current asphalt surface on the southbound lane is not the finished product. An additional layer of black base asphalt will be added, followed by the final surface layer to complete the roadway.

If you experience any issues during construction, please contact Construction Manager Ed Lloyd at 281-660-8737 or by email at This email address is being protected from spambots. You need JavaScript enabled to view it..

Traffic pattern:

05 16 2025 Vlinc map

_______________________________________________________________________________________________

May 21, 2025 | Construction on the southbound lane of Bunker Hill Rd. continues to progress. Beginning the week of May 26, 2025, crews are expected to transition construction to the northbound lane. Traffic will be restricted to one-way southbound travel only between Memorial and Taylorcrest as work on the northbound lane is completed. Drivers are urged to plan their route accordingly and follow recommended detour signage during construction.

Attempting to travel northbound in the southbound lane at any time is strictly prohibited.  MVPD will continue traffic enforcement efforts for the safety of all motorists and construction crews.

If you experience any issues during construction, please contact Construction Manager Ed Lloyd at 281-660-8737 or by email at This email address is being protected from spambots. You need JavaScript enabled to view it..

_______________________________________________________________________________________________

May 16, 2025 | The City’s contractor, Hayden Pavement, continues construction on the southbound lane of Bunker Hill Rd. During the week of May 19, 2025, crews will begin to transition construction to the northbound lane. Traffic will be restricted to one-way southbound travel only between Memorial Dr. and Taylorcrest Rd. as work on the northbound lane is completed. Drivers are urged to plan their route accordingly and follow recommended detour signage during construction.

MVPD will continue traffic enforcement efforts for the safety of all motorists and construction crews.

If you experience any issues during construction, please contact Construction Manager, Ed Lloyd at 281-660-8737 or by email at This email address is being protected from spambots. You need JavaScript enabled to view it..

Traffic pattern beginning the week of May 19, 2025:

05 16 2025 Vlinc map

_______________________________________________________________________________________________

May 2, 2025 | The City’s contractor, Hayden Pavement, began construction on the southbound lane of Bunker Hill Rd. the week of April 28. Traffic is restricted to one-way northbound travel only between Memorial Dr. and Taylorcrest Rd. as work on the southbound lane is completed. Drivers are urged to plan their route accordingly and follow recommended detour signage during construction. 

Please be advised that drivers attempting to travel southbound in the northbound lane at any time will be subject to traffic enforcement by MVPD.  Wrong-way drivers are a public safety hazard to all motorists and construction crews. 
 
Construction on Taylorcrest Rd. is tentatively scheduled to start in June after the school year.
 
If you experience any issues during construction, please contact Construction Manager, Ed Lloyd at 281-660-8737 or by email at This email address is being protected from spambots. You need JavaScript enabled to view it..
 
Traffic pattern: 
05 02 2025 Vlinc Map

_______________________________________________________________________________________________

April 16, 2025 | The City hosted two (2) Town Hall Meetings to discuss upcoming road improvements on Bunker Hill Rd. and Taylorcrest Rd. At the meetings, City staff, the project engineer, and the contractor shared details about the construction process, project timeline, and proposed traffic control plans.

  • To watch a video recording of the first Town Hall Meeting held on Wednesday, April 9, 2025, CLICK HERE
  • To view the presentation slides, CLICK HERE

Beginning the week of April 21, the City’s contractor, Hayden Pavement, will begin mobilizing on Bunker Hill Rd. installing traffic control devices ahead of construction work.  Construction will begin on the southbound lane the week of April 28.  Travel will be restricted to northbound travel only between Memorial and Taylorcrest while the southbound lane work is completed. Drivers are urged to plan their route accordingly and follow recommended detour signage during construction. Construction on Taylorcrest Rd. is tentatively scheduled to start in June after the school year.

Please note that the construction process will be disruptive to area residents in and around the construction zone. Project staff will make every effort to mitigate disruptions as much as possible. 
 
If you experience any issues during construction, please contact Construction Manager, Ed Lloyd at 281-660-8737 or by email at This email address is being protected from spambots. You need JavaScript enabled to view it.. 
 
Regular project updates will be made available on the City's website and be sent out via V-linc.

_______________________________________________________________________________________________

March 28, 2025 | The City will host two (2) town hall meetings to discuss upcoming road improvements on Bunker Hill Rd. and Taylorcrest Rd. Residents will learn about the construction process, project timeline, and proposed traffic control plans. This meeting is also an opportunity for residents and the general public to ask questions directly to City staff, the project engineer, and the contractor about this work.

Town Hall Meeting Location, Dates & Times
Bunker Hill Village City Hall (11977 Memorial Dr., Houston, TX 77024) 
  • Wednesday, April 9, 2025 | 5:30 p.m. 
  • Monday, April 14, 2025 | 9:00 a.m. 
Residents are strongly encouraged to attend to learn information on what to expect from this project. Please note that the construction process will be disruptive to area residents in/ around the construction zone. Project staff will make every effort to mitigate disruptions as much as possible. 
Beginning the week of April 21, the City’s contractor, Hayden Pavement, will mobilize to prepare for the start of construction on the southbound lane Bunker Hill Rd. the week of April 28. Construction on Taylorcrest Rd. is tentatively scheduled to start in June after the school year. 
 
 
  • To watch a video recording of the first Town Hall Meeting held on Wednesday, April 9, 2025, CLICK HERE
  • To view the presentation slides, CLICK HERE