July 24, 2025 | Beginning the week of July 28, 2025, crews will apply roadway and crosswalk striping to both Bunker Hill Rd. and Taylorcrest Rd. Flaggers will be present to direct vehicles through the area safely; however, drivers should expect temporary delays as striping is completed. No long-term lane closures are anticipated. 

Drivers are urged to continue exercising caution in construction zones as crews will remain on-site to complete punch list items (i.e., manhole leveling, site cleanup operations, etc.). 

If you experience any issues during construction, please contact Construction Manager, Ed Lloyd at 281-660-8737 or by email at This email address is being protected from spambots. You need JavaScript enabled to view it..

_______________________________________________________________________________________________

July 17, 2025 | The City’s contractor, Hayden Pavement, has substantially completed road improvements on Bunker Hill Rd. and Taylorcrest Rd.

Bunker Hill Rd. Reconstruction – Beginning the week of July 21, 2025, crews will apply roadway striping to Bunker Hill Rd. between Memorial and Taylorcrest. Flaggers will be present to direct vehicles through the area safely; however, drivers should expect temporary delays as striping is completed. No long-term lane closures are anticipated. 

Taylorcrest Rd. Improvement – The mill and overlay work on Taylorcrest Rd. is substantially complete, with both lanes now open to traffic. Drivers are urged to continue exercising caution in the area as crews will remain on-site to complete punch list items (i.e., manhole leveling, site cleanup operations, etc.). Road and crosswalk striping work will be scheduled within the next 3-4 weeks.

If you experience any issues during construction, please contact Construction Manager, Ed Lloyd at 281-660-8737 or by email at This email address is being protected from spambots. You need JavaScript enabled to view it..

_______________________________________________________________________________________________

July 10, 2025 | Beginning the week of July 14, 2025, the City’s contractor, Hayden Pavement, will start the asphalt overlay of Taylorcrest Rd. between Strey Ln. and Blalock Rd. Asphalt paving work will take place in the following phases:

Phase 2A – Eastbound Lane Closure

  • Traffic will be restricted to one-way westbound travel only as work on the eastbound lane is completed first. 

Phase 2B – Westbound Lane Closure 

  • Traffic will then be restricted to one-way eastbound travel only as work on the westbound lane is completed. 

Flaggers will be present during the day, however drivers should expect traffic delays. Drivers are urged to plan their route accordingly and follow recommended detour signage during construction. All lanes will be open to traffic during the nighttime hours.

If you experience any issues during construction, please contact Construction Manager, Ed Lloyd at 281-660-8737 or by email at This email address is being protected from spambots. You need JavaScript enabled to view it..

Project phases:

07 10 2025 project map

_______________________________________________________________________________________________

July 2, 2025 | The reconstruction of Bunker Hill Rd. is substantially complete. Effective the evening of Thursday, July 3, 2025, both lanes of Bunker Hill Rd. will be open to traffic. Drivers are urged to exercise caution in the area as crews will remain in the area to complete punch list items (i.e., manhole leveling, site cleanup operations, etc.). Please note that the road must cure for a minimum of 14 days prior to completing final striping. Temporary marking will be in place in the interim. 

Beginning Monday, July 7, 2025, the City’s contractor, Hayden Pavement, will begin the mill and overlay of Taylorcrest Rd. Road milling work will take place in the following phases:

Phase 1A – Strey Ln. to Bunker Hill Rd.

  • Traffic will be restricted to one-way westbound travel only as work on the eastbound lane is completed first.
  • Traffic will then be restricted to one-way eastbound travel only as work on the westbound lane is completed.

Phase 1B – Bunker Hill Rd. to Blalock Rd.

  • Traffic will be restricted to one-way westbound travel only as work on the eastbound lane is completed first.
  • Traffic will then be restricted to one-way eastbound travel only as work on the westbound lane is completed. 

Flaggers will be present during the day, however drivers should expect traffic delays. Drivers are urged to plan their route accordingly and follow recommended detour signage during construction. All lanes will be open to traffic during the nighttime hours.

Project phases: 

Taylorcrest_Rd._Project_Phase_Map.png

 

If you experience any issues during construction, please contact Construction Manager, Ed Lloyd at 281-660-8737 or by email at This email address is being protected from spambots. You need JavaScript enabled to view it..

_______________________________________________________________________________________________

May 30, 2025 | Construction continues on the northbound lane of Bunker Hill Rd. Traffic is restricted to one-way southbound travel only between Memorial and Taylorcrest as work on the northbound lane is completed. Drivers are urged to plan their route accordingly and follow recommended detour signage during construction.

Attempting to travel northbound in the southbound lane at any time is strictly prohibited. MVPD will continue traffic enforcement efforts to ensure the safety of all motorists and construction crews.

Please note that the current asphalt surface on the southbound lane is not the finished product. An additional layer of black base asphalt will be added, followed by the final surface layer to complete the roadway.

If you experience any issues during construction, please contact Construction Manager Ed Lloyd at 281-660-8737 or by email at This email address is being protected from spambots. You need JavaScript enabled to view it..

Traffic pattern:

05 16 2025 Vlinc map

_______________________________________________________________________________________________

May 21, 2025 | Construction on the southbound lane of Bunker Hill Rd. continues to progress. Beginning the week of May 26, 2025, crews are expected to transition construction to the northbound lane. Traffic will be restricted to one-way southbound travel only between Memorial and Taylorcrest as work on the northbound lane is completed. Drivers are urged to plan their route accordingly and follow recommended detour signage during construction.

Attempting to travel northbound in the southbound lane at any time is strictly prohibited.  MVPD will continue traffic enforcement efforts for the safety of all motorists and construction crews.

If you experience any issues during construction, please contact Construction Manager Ed Lloyd at 281-660-8737 or by email at This email address is being protected from spambots. You need JavaScript enabled to view it..

_______________________________________________________________________________________________

May 16, 2025 | The City’s contractor, Hayden Pavement, continues construction on the southbound lane of Bunker Hill Rd. During the week of May 19, 2025, crews will begin to transition construction to the northbound lane. Traffic will be restricted to one-way southbound travel only between Memorial Dr. and Taylorcrest Rd. as work on the northbound lane is completed. Drivers are urged to plan their route accordingly and follow recommended detour signage during construction.

MVPD will continue traffic enforcement efforts for the safety of all motorists and construction crews.

If you experience any issues during construction, please contact Construction Manager, Ed Lloyd at 281-660-8737 or by email at This email address is being protected from spambots. You need JavaScript enabled to view it..

Traffic pattern beginning the week of May 19, 2025:

05 16 2025 Vlinc map

_______________________________________________________________________________________________

May 2, 2025 | The City’s contractor, Hayden Pavement, began construction on the southbound lane of Bunker Hill Rd. the week of April 28. Traffic is restricted to one-way northbound travel only between Memorial Dr. and Taylorcrest Rd. as work on the southbound lane is completed. Drivers are urged to plan their route accordingly and follow recommended detour signage during construction. 

Please be advised that drivers attempting to travel southbound in the northbound lane at any time will be subject to traffic enforcement by MVPD.  Wrong-way drivers are a public safety hazard to all motorists and construction crews. 
 
Construction on Taylorcrest Rd. is tentatively scheduled to start in June after the school year.
 
If you experience any issues during construction, please contact Construction Manager, Ed Lloyd at 281-660-8737 or by email at This email address is being protected from spambots. You need JavaScript enabled to view it..
 
Traffic pattern: 
05 02 2025 Vlinc Map

_______________________________________________________________________________________________

April 16, 2025 | The City hosted two (2) Town Hall Meetings to discuss upcoming road improvements on Bunker Hill Rd. and Taylorcrest Rd. At the meetings, City staff, the project engineer, and the contractor shared details about the construction process, project timeline, and proposed traffic control plans.

  • To watch a video recording of the first Town Hall Meeting held on Wednesday, April 9, 2025, CLICK HERE
  • To view the presentation slides, CLICK HERE

Beginning the week of April 21, the City’s contractor, Hayden Pavement, will begin mobilizing on Bunker Hill Rd. installing traffic control devices ahead of construction work.  Construction will begin on the southbound lane the week of April 28.  Travel will be restricted to northbound travel only between Memorial and Taylorcrest while the southbound lane work is completed. Drivers are urged to plan their route accordingly and follow recommended detour signage during construction. Construction on Taylorcrest Rd. is tentatively scheduled to start in June after the school year.

Please note that the construction process will be disruptive to area residents in and around the construction zone. Project staff will make every effort to mitigate disruptions as much as possible. 
 
If you experience any issues during construction, please contact Construction Manager, Ed Lloyd at 281-660-8737 or by email at This email address is being protected from spambots. You need JavaScript enabled to view it.. 
 
Regular project updates will be made available on the City's website and be sent out via V-linc.

_______________________________________________________________________________________________

March 28, 2025 | The City will host two (2) town hall meetings to discuss upcoming road improvements on Bunker Hill Rd. and Taylorcrest Rd. Residents will learn about the construction process, project timeline, and proposed traffic control plans. This meeting is also an opportunity for residents and the general public to ask questions directly to City staff, the project engineer, and the contractor about this work.

Town Hall Meeting Location, Dates & Times
Bunker Hill Village City Hall (11977 Memorial Dr., Houston, TX 77024) 
  • Wednesday, April 9, 2025 | 5:30 p.m. 
  • Monday, April 14, 2025 | 9:00 a.m. 
Residents are strongly encouraged to attend to learn information on what to expect from this project. Please note that the construction process will be disruptive to area residents in/ around the construction zone. Project staff will make every effort to mitigate disruptions as much as possible. 
Beginning the week of April 21, the City’s contractor, Hayden Pavement, will mobilize to prepare for the start of construction on the southbound lane Bunker Hill Rd. the week of April 28. Construction on Taylorcrest Rd. is tentatively scheduled to start in June after the school year. 
 
 
  • To watch a video recording of the first Town Hall Meeting held on Wednesday, April 9, 2025, CLICK HERE
  • To view the presentation slides, CLICK HERE